G.O. Bond Road: Abrazo Road - Complete

Project Manager: Gillie Lopez
Office Phone: (505) 891-5049
E-Mail: glopez@rrnm.gov
Contract Company: Franklins Earthmoving Inc.
Cost: $  2,417,104.16
Stage: Construction
Schedule: Complete
Abrazo2
Final design and technical specifications to reconstruct Abrazo Road from Unser Boulevard to Chessman Drive, will include sidewalk, curb & gutter, Americans with Disabilities Act (ADA) compliant curb ramps, and street lighting as needed. The design will also include a new 8" water line to replace the existing water line as well as service lines to all platted lots along Abrazo Road from Unser Boulevard to Chessman Drive; and the design for a new 8" sewer line, manholes, stub outs to side streets, and sewer services to existing platted lots from Gemini Road to Encantado Ridge Court.

Additional Information:


Current Traffic Control:


Work for the Abrazo Road Project from Unser Boulevard to Chessman Drive will be from January 14, 2019 - July 2019.  During construction there will be detours, speed limit reductions, and regular construction noise.  Click here to see the most current Detours for the project.

Status Log:

  • December 2018:  Abrazo Road is expected to begin Construction January 14, 2019 and last until July 2019.
  • November 2018: Project is currently being Bid.
  • September 2018: 90% Design plans are being reviewed and finalized.
  • August 2018: 60% Design plans were reviewed. 90% Design in process.
  • July 2018: 30% Design plans were reviewed. 60% Design in process.
  • June 2018: Design Process started.
  • May 2018:  Design Services was awarded to Wilson & Company. The kick-off meeting and field review was held on 5/30/18.