US 550 Phase 2

NMDOT Contact: Patsy Najar
Office Phone: (505) 401-9702
E-mail: patsy.najar@state.nm.us
Contract Company: FNF
Cost: $  23,826,023.50
Stage: Construction
Schedule: October 2019 - June 2021 
US 550 & Rio Grande Bridge
US 550 Phase 2 is managed by the New Mexico Department of Transportation (NMDOT).  This project will consist of new bridge construction, roadway reconstruction, signalization, and lighting along US 550 from Mile Post 1.368 to Mile Post 2.331.  For more information please go to www.keepmoving550.com or www.nmroads.com.  Please see the Current Road Work page for details on the construction.

Status Update

October 2019:
  • Construction will begin on October 28, 2019 with a contract length f 600 calendar days for construction.